Mile-Long Tunnel To Support UNC Enrollment Growth Keywords: construction methods, analysis, legislation, ENR, equipment & materials, engineering news-record, labor, costs
Full Article Price:
$4.95 Delivery: Immediate Online Access
Publication Date: 16-MAY-05 Format: XML document
|
 |
Article Description| Construction is proceeding in three phases, including one for the utility plant and two for separate tunnels connecting to the plant. Together, construction costs total $84 million. A joint venture of Whitaker Construction and Associated Brigham Contractors (ABC), both of Brigham City, Utah, expects to complete its lump-sum contract for 3,000 ft of tunnel in September. Clancy and Theys and ... |
|
|
 |
Subscribe to ENR |
|
|
|
 |
|
|
Subscribe to ENR Try 4 issues FREE!
Monthly Subscription only $9.95/month